2013年7月2日星期二

BFW-type chain conveyor what you most want to know




BFW-type chain conveyor, is a type of conveyor, about it, and today we want to introduce what it? Here is not summed up, the reader, after reading this article, you will

understand.
One, BFW-type chain conveyor installation
1 box testing, mainly to see the parts are complete, without damage, check and correct, it can be based installation, as well as to determine a good central location centerline,

and then pouring concrete for, and then to carry out maintenance on the basis of . Maintenance period of time, and no correction

Mistake, you can carry out the installation of the device.Gravity roller conveyor
(2) Before installation, respond to the various components for cleaning, removing rust grease, and be checked. The hole must also be based on the clean-up examination in order

to be able to install in place.
3 on the basis of the rack to hang, and then bolt into the foot, installed after the installation of tracks installed, right sprocket unit, tail wheel device, tensioning device

and chain plate for installation. Finally installing the motor, reducer, and other devices.
4 all parts of the mounting accuracy requirements:
(1) the center line of the conveyor frame to coincide with the longitudinal centerline, the deviation is not greater than 2mm.
(2) between two adjacent brackets, the horizontal deviation is not greater than 2mm.
(3) straight track deviation is not greater than 1.5mm / m, and the deviation of the line length is not greater than 5mm.skate roller conveyor
(4) the cross section of the same, the relative elevation of the track deviation is not greater than 2mm.
(5) the axis of the drive sprocket of the vertical center line of the conveyor deviation is not greater than 1mm / m, the chain between two lateral center of the deviation of

the center line and the whole is not greater than 1mm.
(6) tail wheel horizontal axis deviation is not greater than 1mm / m.
(7) deviation of the horizontal roller shaft is not greater than 1mm, the bus should be in the same horizontal plane, the level of deviation is not greater than 1mm.
Two, BFW-type chain conveyor use
1 as uniform as possible feeding, and its maximum size should be in the control range.
2 conveyor is full, is not suitable for stopping and starting.
3. The traction chain and elastic sleeve roller chain should be appropriate, so always check to make timely adjustments.
Three, BFW-type chain conveyor maintenance
1 conveyor lubrication should always check regularly add oil.
2 reducer most starts running, run 7-14 days, to replace oil, after 3-6 months to replace it once, depending on the circumstances.
3 Always check for any loose bolts, bearing temperature does not exceed the range, and there is no motor current exceeds the rated current, etc., if any should stop to check.
4 should be based on usage and maintenance on the conveyor half again, and making a good maintenance plan to ensure normal operation of equipment.

没有评论: