Zhengzhou Modern Automation Equipment Co., LTD plastic plate chain conveyor using iron bending forming, conveyor transfer method using plastic chain plate, mainly for food and beverage delivery, or forced into continuous operation tempo control, cycle time according to the product adjustment process requirements, powered by ordinary motor, electromagnetic speed motor, inverter variable speed motor, mechanical variable speed motor, speed adjustable.
2013年7月7日星期日
Introduction board chain bucket elevator installation requirements
1 board chain bucket elevator tail wheel base body supporting surface, must ensure that the surface is located in the basal level and the level meter with a box-type flange
catchy leveling.
2 board chain bucket elevator shaft upper and lower tensioning shaft shall be in the same vertical plane, and the two lines should be parallel to the horizontal axis.
3 intermediate casing flange connections, without significant dislocation between the flanges can pad into asbestos rope or waterproof canvas to ensure the seal.
4 board chain bucket elevator lower section and an upper section of the intermediate casing centerline should be in the same vertical line, the vertical deviation at 1 m length
must not exceed 1 mm total height cumulative deviation Allow more than 8 mm.
5 Hopper joins the traction chain should be positioned correctly with bolts and traction chain hopper turtle shell coupling fastened.
6 board chain bucket elevator rail section should be installed in the elevator in the lower side.Automatic Sorting Machine
7 the end of the chain tensioning device set to the highest position, install upgrade chain, the drag chain tensioning device to adjust a uniform, normal operation of the
tensioning force necessary.
8 speed reducer shaft axis and the drive axis to be parallel to the hoist, the maximum angle between the axis of no more than 40 degrees, the size of the chain to be in the same
plane.
9 board chain bucket elevator Central should prevent shifting means, supporting points spaced not more than 8 meters, the top support should be as close to the head. Outdoor
installation taut rope hoist should be taut.
10 board chain bucket elevator installed, the transmission parts and gear should refuel, remove the ratchet wheel cover, or remove the ratchet belt, try reversing the motor, the
motor turned to the right, adjust the material adjustment board to operate without scraping hopper appropriate.Food conveyor
11 pre-commissioning checks whether there is debris hoist, if should be promptly removed, hoist check once again the overall test run; adjust the tensioning device
commissioning, commissioning adjusted once after 4 hours and tighten the tensioning device solid hopper bolts, nuts and after trial run 72 bolts welded.
Equipment operation tensioning device inspected once a month later.